Level |
Project description
|
Project Level I |
Project made up of elements with unit weights of less than 500 kg. The engineering is developed by the client.
|
Project Level II |
Project made up of elements whose weight per unit is less than 5,000 kg. It may include on-site assembly and the engineering is developed by the client.
|
Project Level III |
Project preferably made up of several elements whose total weight is greater than 5,000 kg. It may include on-site assembly and the engineering is developed by the client.
|
Project Level IV |
Project made up of one or more elements. The unit weight or as a whole must be less than 5,000 kg. May include on-site assembly and the engineering is developed by TAMA.
|
Project Level V |
Project made up of one or more elements. The unit weight or as a whole must be greater than 5,000 kg. May include on-site assembly and the engineering is developed by TAMA.
|
Project Level VI |
Complete plants and/or systems that include other disciplines: civil works, electrical works and on-site assembly. The engineering is developed by TAMA or by the customer.
|
Project Level VII |
Customer service where one or more areas are involved. Likewise, the TAMA operation process is directly involved.
|
Project Level VIII |
Service to customers where TAMA operation process is not involved (for example, engineering services, warehouse, quality control, etc.). May include work at the customer’s plant or facilities.
|